A concrete takeoff comes down to volumes: length × width × thickness. Mistakes rarely come from the multiplication. They come from units (inches, feet and cubic metres mixed together), from a wall length measured to the wrong face, or from formwork and rebar left out. Here's a clear method, with a complete example.

What you need before you start

Cubic metres or cubic yards

In Québec, concrete is ordered in cubic metres (m³). Elsewhere in North America, cubic yards (yd³) are common. The conversion:

The most common trap: multiplying feet by inches. Convert everything to the same unit before you multiply (e.g. 10" = 0.833 ft), or let a tool do it for you.

1. Strip footing

Footing formwork covers both sides:

Footing rebar is counted in continuous bars:

Laps (bar overlaps) are covered here by a percentage, often around 10%. If your drawings call for specific lap lengths, you can also count them bar by bar.

2. Foundation wall

Wall rebar has two parts:

Anchor bolts follow the same logic: length ÷ spacing, rounded up, + 1 per wall. Also add dampproofing (length × height) and weeping tile (length, plus a small margin).

3. Slab

The materials under and in the slab use the same area: rigid insulation, 6 mil poly and wire mesh, the last two with about 10% extra for overlaps. Measure the area inside the foundation walls, not the outside footprint.

4. Isolated footings and columns

Isolated footings (under columns or posts) don't all have the same size. The simplest way: trace each one in plan as a rectangle (an area), then multiply:

Concrete columns work the same way, with height instead of thickness. A round column is traced as a circle: concrete is area × height and the form (cardboard tube) has the same height. Ties are counted from their spacing: (height ÷ spacing, rounded up, + 1) × column perimeter.

Worked example: a bungalow foundation

Assumptions (common values, to replace with those on your drawings):

Concrete

ItemCalculationResult
Footing136 × 2 × 0.833 = 226.7 cu. ft = 6.42 m³, × 1.056.74 m³ (8.81 yd³)
Wall136 × 8 × 0.667 = 725.3 cu. ft = 20.54 m³, × 1.0521.57 m³ (28.21 yd³)
Slab1,000 × 0.333 = 333.3 cu. ft = 9.44 m³, × 1.059.91 m³ (12.96 yd³)
Isolated footings3 × 4 sq. ft × 1 = 12 cu. ft = 0.340 m³, × 1.050.36 m³

In total, about 38.6 m³ of concrete, in three or four separate pours. Order each pour separately and round up according to your supplier's requirements: the footing and the slab don't go in the same truck.

Formwork and rebar

ItemCalculationResult
Footing formwork136 × 0.833 × 2226.7 sq. ft
Wall formwork136 × 8 × 22,176 sq. ft
Footing rebar136 × 2 = 272, × 1.10299.2 lin. ft
Wall horizontal rebar136 × 3 = 408, × 1.10448.8 lin. ft
Wall vertical rebar136 ÷ 2 = 68, + 4 walls = 72 bars × 8 = 576, × 1.10633.6 lin. ft
Anchor bolts136 ÷ 6 = 22.7 → 23, + 4 walls27 bolts
Isolated footing formworkperimeter 3 × 8 = 24 ft × 124 sq. ft
Isolated footing rebar4 × 24 ÷ 2 = 48, × 1.1052.8 lin. ft

Key points:

Common mistakes

In KOR

KOR includes starter templates for foundations, using the rules in this article, all editable: "Footing and foundation wall" (trace the wall length at the centre; footing and wall concrete in m³, formwork, rebar, anchor bolts, dampproofing, weeping tile), "Concrete slab" (trace the area), "Isolated footings (piers, columns)" and "Concrete columns" (each traced as a rectangle, or a circle for a round column, with its own dimensions). Units are converted automatically, the math runs on each item's total, and the quantities go straight into the estimate.

Summary

  1. Measure foundation walls at the centre, and convert every dimension to the same unit.
  2. Concrete = length × width (or height) × thickness, + waste; slab = area × thickness, + waste.
  3. Formwork = length × thickness or height × 2 sides; isolated footings and columns: perimeter × thickness or height.
  4. Rebar: continuous bars × length, vertical bars from the spacing, + laps.
  5. Order concrete pour by pour.