General conditions are the job costs you can't measure on the drawings: the people running the work, temporary facilities, dumpsters, permits, insurance. No takeoff will produce them for you. That's exactly why they get forgotten, or thrown in as a guess. Here's a checklist by category, how to price each line, and a complete example.

General conditions vs. overhead

The two get mixed up all the time. They don't cover the same costs.

The simple test: if the cost goes away when the job is done, it's a general condition. If it keeps going, it's overhead. And each cost goes in one place only, never both.

The checklist, by category

Staff

Site facilities

Waste and cleaning

Permits and fees

Insurance and bonds

How to quantify each line

Each category has its own unit. That's what makes general conditions checkable.

Worked example: a 16-week house

Assumptions: 16-week job (112 days, so 4 months of rental), 2 winter months to heat, 6 dumpster pickups.

LineCalculationAmount
Project manager4 h/wk × 16 wk = 64 h × $75$4,800
Foreman10 h/wk × 16 wk = 160 h × $65$10,400
Labourer8 h/wk × 16 wk = 128 h × $40$5,120
Staff$20,320
Site toilet4 months × $200$800
Temporary power4 months × $150$600
Site fencing4 months × $250$1,000
Temporary heat2 months × $1,500$3,000
Protection and signage1 lump sum × $1,500$1,500
Site facilities$6,900
Dumpsters6 pickups × $600$3,600
Final cleaning1 lump sum × $1,200$1,200
Waste and cleaning$4,800
Building permit1 lump sum × $3,000$3,000
Job insurance1 lump sum × $2,500$2,500
Total general conditions20,320 + 6,900 + 4,800 + 3,000 + 2,500$37,520

If the job runs 4 weeks longer

The same project now takes 20 weeks (140 days, so 5 months of rental):

That's $5,680 more, without a single extra stick of material. This is why general conditions need to be tied to the actual length of the job, not typed in once and forgotten.

Common mistakes

In KOR

In KOR, the "General conditions" section always sits at the top of the estimate, even when it's empty, so it doesn't get forgotten. You can start from a usual list (staff in hours, site facilities, waste and cleaning, permits and fees, insurance and bonds) that comes without prices: you enter your own rates once, in the Library, then add it to each project. Rental lines can follow the project schedule's duration, in weeks or months: if the schedule gets longer, the quantity follows.

Summary

  1. General conditions = costs of this job; overhead = costs of the office. Each cost in one place only.
  2. Staff in hours, rentals by the week or month from the schedule duration, permits and insurance as lump sums.
  3. A rental month that has started is often billed in full.
  4. Heat only for the job's winter months.
  5. When the duration changes, update the hours and the rentals.